Example Asbestos Removal Projects in Redondo Beach

Seven example jobs follow, from a townhouse stair landing to a kitchen opened into a family room. Every one lists what was sampled, what was removed, the work days and an estimated cost.

Ceiling and joint compound removed before beams are exposed in a cottage living room

Example project

Home
1950s cottage in Redondo Beach with a flat drywall ceiling in the living room
Original request
Take the living room ceiling down to expose the beams and refinish them
Testing
A Cal/OSHA-certified asbestos consultant samples the ceiling drywall, its taped joints and the top of the wall at three points
Found
Asbestos in the joint compound and the skim coat on the ceiling
Clear
The drywall panels themselves
Area
About 400 sq ft of ceiling and upper wall
Timeline
Notice no later than 10 working days ahead, then three working days
Cost
$4,400

Scope of work

The living room sealed in plastic with air filters running, the positive compound and skim coat taken off wet and the panels pulled down, bagged disposal and a cleanup. The survey, the district notification fee, the clearance air test, the beam refinishing and the new lights are separate.

Project overview

In this example, a couple wants the beams in their 1950s cottage to show. Taking the ceiling down is a renovation, so the survey comes first, and the job is large enough to need the district notice.

The taped joints and the skim coat test positive. The abatement contractor files the notice online, and the abatement crew removes the ceiling in one sealed pass before the carpenter starts on the beams.

The goal

The goal is an open ceiling with the positive layers gone, so the beams are refinished in a clean room.

Process

  1. First visit A Cal/OSHA-certified asbestos consultant samples the panels, the joints and the skim coat.
  2. Before work The abatement contractor files the district notice online.
  3. Days one to three The living room is sealed and the ceiling comes down in sections.
  4. Last An independent consultant tests the air, then the carpenter starts on the beams.

Planning right

  • Empty the room, including the wall hangings.
  • Ask where the lights and wires above the ceiling will be re-run.
  • Hold the beam stain until the air results are in.
  • Keep the report with the remodel plans.

Get a free quoteMore about drywall, joint compound and plaster removal

Sheet vinyl and glue removed from a townhouse stair landing

Example project

Home
1970s townhouse in Redondo Beach with sheet vinyl on the stair landing and the three steps below it
Original request
Strip the landing and steps for new stair treads
Testing
A Cal/OSHA-certified asbestos consultant samples the sheet vinyl and the glue under it on the landing and on a step
Found
Asbestos in the vinyl backing and the glue
Area
About 60 sq ft of landing and steps
Timeline
Less than 100 square feet in a renovation, so no district notice, then one working day
Cost
$1,600

Scope of work

The stairwell sealed with plastic and a filter running, the vinyl lifted and the glue removed wet, bagged disposal and a cleanup. The survey, the treads and the finish are separate.

Project overview

In this example, the owner of a 1970s townhouse is replacing the worn stair covering. A townhouse is not a single-unit dwelling to the district, so the survey comes first, even for a small job.

The vinyl and its glue test positive. A renovation removing less than 100 square feet skips the district notice, so the abatement crew can work the next available day and the stair carpenter follows.

The goal

The goal is a bare landing and bare steps, so the new treads are fastened to a surface with nothing positive on it.

Process

  1. First visit A Cal/OSHA-certified asbestos consultant samples the landing and one step.
  2. Results The lab marks the vinyl backing and the glue positive.
  3. Work day The stairwell is sealed and the vinyl and glue are removed wet.
  4. Then The stair carpenter sets the new treads.

Planning right

  • Move shoes and bins off the stairs.
  • Plan how the household gets up and down on the work day.
  • Order the treads after the work day.
  • Pass the report on to the homeowners association file.

Get a free quoteMore about floor tile and mastic removal

Eight samples from two bathrooms before a duplex is listed

Example project

Home
1940s duplex in Hermosa Beach with a bathroom in each unit, tile floors and plaster walls
Original request
Learn what the bathrooms hold before the building goes on the market
Testing
A Cal/OSHA-certified asbestos consultant samples the floor tile and mastic, the wall plaster and the ceiling texture in each bathroom
Found
Asbestos in the mastic under the tile in one bathroom
Clear
The other mastic, both plaster walls and both ceilings
Timeline
Lab results first, then the listing agent gets the report
Estimated testing cost
$650

Scope of work

A visit by the consultant, eight samples, a lab result for each and a short report with the spots marked. Removing the mastic is priced on its own.

Project overview

In this example, two siblings inherited a 1940s duplex in Hermosa Beach and want to sell it. Buyers ask what the bathrooms contain, so the sampling comes before the listing.

Eight samples cover both units. One mastic tests positive and everything else is clear, so the siblings can choose whether to have that bathroom floor removed before the sale or share the report with buyers.

The goal

The goal is a written answer for both bathrooms, so the sale does not stall on a question nobody checked.

Process

  1. First visit A Cal/OSHA-certified asbestos consultant samples the floor, the walls and the ceiling in each bathroom.
  2. Results The report marks one mastic positive and the other seven samples clear.
  3. Decision The siblings weigh removal against listing as is.
  4. Then The listing agent gets the lab report.

Planning right

  • Give the consultant access to both units on the visit.
  • Send the report to the agent with the listing papers.
  • Ask the consultant to mark each sample on a sketch.
  • Leave the sampling to the consultant.

Get a free quoteMore about asbestos testing and surveys

Wall and floor material removed before a kitchen and family room become one room

Example project

Home
1960s ranch house in Palos Verdes Estates with a wall between the kitchen and the family room
Original request
Take out the wall between the rooms and set a beam in its place
Testing
A Cal/OSHA-certified asbestos consultant samples the wall texture and joint compound on both faces and the kitchen sheet vinyl and glue
Found
Asbestos in the joint compound and in the kitchen vinyl and glue
Clear
The wall texture
Area
About 160 sq ft of wall and floor
Timeline
Notice no later than 10 working days ahead, then three working days
Cost
$4,900

Scope of work

The kitchen and family room sealed with air filters running, the positive compound and the vinyl with its glue removed wet, bagged disposal and a cleanup. The survey, the district notification fee, the clearance air test, the framing and the new floor are separate.

Project overview

In this example, the owners of a 1960s ranch house are joining the kitchen and the family room. The wall is load-supporting and gets a beam, and taking out a load-supporting member counts as demolition, so the district notice is always required.

The joint compound and the kitchen vinyl test positive. The abatement crew removes them before the framers shore up the roof and cut the wall out.

The goal

The goal is an open floor plan whose old wall and floor materials are already gone when the framers arrive.

Process

  1. First visit A Cal/OSHA-certified asbestos consultant samples the wall on both sides and the kitchen floor.
  2. Before work The abatement contractor files the district notice online.
  3. Days one to three Both rooms are sealed and the compound and the vinyl come out wet.
  4. Last An independent consultant tests the air, then the framers start.

Planning right

  • Empty the kitchen cabinets on the wall side.
  • Share the report with the framer and the engineer.
  • Keep the district notice with the permit papers.
  • Order the beam after the plan is final.

Get a free quoteMore about renovation and demolition abatement

Bedroom ceiling texture removed before a ceiling fan goes in a condominium

Example project

Home
1970s condominium in Redondo Beach with a textured ceiling in the primary bedroom
Original request
Hang a ceiling fan with a new light and wiring through the ceiling
Testing
A Cal/OSHA-certified asbestos consultant samples the ceiling texture at the fan spot and two other points
Found
Asbestos in the texture at all three points
Area
About 145 sq ft of bedroom ceiling
Timeline
Notice no later than 10 working days ahead, then two working days
Cost
$1,900

Scope of work

The bedroom sealed in plastic with air filters running, the texture wetted and scraped into bags, a HEPA clean and the haul. The survey, the district notification fee, the clearance air test, the patching and the fan are separate.

Project overview

In this example, a condominium owner wants a ceiling fan over the bed. The electrician needs to cut into the ceiling, and a condominium is never a single-unit dwelling, so the survey comes first.

The texture tests positive at all three points. The ceiling is more than 100 square feet, so the abatement contractor files the district notice online, and the electrician comes once the air results are in.

The goal

The goal is a smooth, bare ceiling, so the fan mounts to a surface with nothing positive left on it.

Process

  1. First visit A Cal/OSHA-certified asbestos consultant samples the ceiling at three points.
  2. Before work The abatement contractor files the district notice online and the owner tells the association.
  3. Days one and two The bedroom is sealed and the texture is wetted and scraped.
  4. Last An independent consultant tests the air, then the electrician hangs the fan.

Planning right

  • Move the bed and dressers out of the bedroom.
  • Tell the neighbors below and above about the work days.
  • Book the electrician after the air results.
  • Ask the association about work hours.

Get a free quoteMore about popcorn ceiling removal

Old tile and mastic removed from a hall and entry after the carpet came up

Example project

Home
1970s two-story house in Redondo Beach with carpet in the upstairs hall and the entry
Original request
Pull up the worn carpet and lay a hard floor
Testing
A Cal/OSHA-certified asbestos consultant samples the 9-inch tile and the mastic under the carpet in the hall and the entry
Found
Asbestos in the tile and the mastic in both spots
Area
About 280 sq ft of hall and entry floor
Timeline
Notice no later than 10 working days ahead, then three working days
Cost
$3,600

Scope of work

The hall and entry sealed with air filters running, the tile lifted and the mastic removed wet, bagged disposal and a cleanup. The survey, the district notification fee, the clearance air test and the new floor are separate.

Project overview

In this example, a family pulled the carpet from the hall and entry of their 1970s house and found old tile underneath. The survey comes first, so they stop and bring in a consultant.

The tile and the mastic test positive. The floor is more than 100 square feet, so the abatement contractor files the district notice online and the abatement crew removes both layers.

The goal

The goal is a bare slab in the hall and entry, so the new hard floor sits on a surface with nothing positive left.

Process

  1. First visit A Cal/OSHA-certified asbestos consultant samples the tile and the mastic in two spots.
  2. Before work The abatement contractor files the district notice online.
  3. Days one to three The hall and entry are sealed, and the tile and mastic are removed wet.
  4. Last An independent consultant tests the air, then the new floor goes in.

Planning right

  • Leave the exposed tile alone until the visit.
  • Choose the new floor while the notice is pending.
  • Keep the family out of the sealed area on work days.
  • Ask the installer about the new floor’s thickness at the doors.

Get a free quoteMore about floor tile and mastic removal

Duct wrap removed at an air handler in an office above a shop

Example project

Home
1960s two-story commercial building in Redondo Beach with a shop below and an office above
Original request
Replace the office air handler and refresh the floor and ceiling
Testing
A Cal/OSHA-certified asbestos consultant samples the duct wrap at the air handler, the floor tile and the ceiling texture
Found
Asbestos in the wrap and tape at the air handler
Clear
The floor tile and the ceiling texture
Area
About 40 sq ft of wrap and tape
Timeline
Less than 100 square feet in a renovation, so no district notice, then one working day
Cost
$2,300

Scope of work

The ceiling space and the office sealed with plastic and a filter running, the positive wrap and tape removed and bagged, and a cleanup. The survey, the new air handler and the floor and ceiling work are separate.

Project overview

In this example, the owner of a two-story commercial building is replacing the air handler above the office. Installing or removing an HVAC system is renovation, and a commercial building is never a single-unit dwelling, so the survey comes first.

Only the wrap and tape at the air handler test positive. The abatement crew takes them off before the HVAC crew arrives, and the floor and the ceiling can be refreshed as planned.

The goal

The goal is an air handler position with the old wrap gone, so the HVAC crew works on clean duct stubs.

Process

  1. First visit A Cal/OSHA-certified asbestos consultant samples the wrap, the floor tile and the ceiling.
  2. Results The report marks the wrap and tape positive and the floor and ceiling clear.
  3. Work day The office and the ceiling space are sealed and the wrap and tape are removed.
  4. Then The HVAC crew replaces the air handler.

Planning right

  • Tell the shop below which day the office is closed.
  • Give the HVAC crew a copy of the report.
  • Move files and desks away from the unit.
  • Order the new air handler after the survey.

Get a free quoteMore about HVAC duct and pipe insulation removal

Request a free asbestos removal quote

We recommend calling, but do feel free to contact us using this form. We'll get back to you with a free, personalized quote or additional questions as soon as possible. We're here to help.

Call (424) 622-0849

Call (424) 622-0849